Kitchen update

Work has now commenced on updating the kitchen, Committee having agreed the specification of work and obtained quotations. Taking into account members’ views, we looked at options for reducing costs and retaining a simple, but practical finish. The new units are a low cost flat packed range with an oven and hob. 

That's dust in the air

A work day last Sunday stripped out the existing units and removed the floor tiles, only to find the sub floor was rotten, so we are having to strengthen and replace that as well. Despite this, the works remain well within budget.  